Get The Most Updated H19-402_V1.0 Dumps To HCSP-Presales-Data Certification
Huawei Certified H19-402_V1.0 Dumps Questions Valid H19-402_V1.0 Materials
NEW QUESTION # 320
The NeEco management system supports remote notification of alarms through SMS, email, etc., prompting users to handle alarms as soon as possible.
- A. True
- B. False
Answer: A
NEW QUESTION # 321
What kind of inlet and outlet wiring methods can the FusionModule2000 integrated power distribution cabinet implement?
- A. Down-in and down-out
- B. Up-line in and down-line out
- C. Lower inlet and upper outlet
- D. Upper inlet and outlet
Answer: D
NEW QUESTION # 322
FusionModule2000's integrated UPS/integrated power distribution cabinet/precision power distribution cabinet can detect branch terminal temperature through NTC probes. This function is optional and unique to Huawei.
- A. True
- B. False
Answer: A
NEW QUESTION # 323
The NetEco6000 management system can provide a temperature cloud map function to identify hot and cold spots in the computer room. How many layers of temperature cloud maps does the temperature cloud map support? (Multiple choice)
- A. Four layers
- B. Double layer
- C. Three layers
- D. Single layer
Answer: B,C,D
NEW QUESTION # 324
Huawei precision air conditioner has RS485 communication interface, which can be used for remote inspection and parameter setting of the system: Modbus open protocol is provided to access the computer room environment monitoring system to reduce service costs.
- A. True
- B. False
Answer: A
NEW QUESTION # 325
Which of the following statements about Fusionmodule surveillance cameras is incorrect?
- A. Camera data can be stored via TF card or hard disk recorder (NVR: Network Video Recorder)
- B. Any number of cameras can be connected to the ETH socket
- C. The camera can be directly connected to a PoE powered switch
- D. The camera is powered by PoE
Answer: B
NEW QUESTION # 326
UPS2000 startup steps:
- A. Closed battery
- B. Close the main bypass circuit breaker
- C. Debugging before power on
- D. Close the output circuit breaker
Answer: A,B,C,D
NEW QUESTION # 327
A system is configured with a 5H battery backup time. The discharge termination voltage of a single battery cell should be selected as ()
- A. 1.75V
- B. 1.80V
- C. 1.67V
- D. 1.60V
Answer: B
NEW QUESTION # 328
Neteco supports centralized management of multiple data centers
- A. True
- B. False
Answer: A
NEW QUESTION # 329
Regarding the overload capacity of UPS5000-E, which of the following statement is correct?
(Multiple choice)
Answer:
Explanation:
A.D.
NEW QUESTION # 330
A system is configured with a 1H battery backup time. The discharge termination voltage of a single battery cell should be selected ().
- A. 1.80V
- B. 1.75V
- C. 1.67V
- D. 1.60V
Answer: B
NEW QUESTION # 331
Which of the following voltage systems does UPS5000-E support? (Multiple choice)
- A. 380V
- B. 415V
- C. 400V
- D. 480V
Answer: A,B,C
NEW QUESTION # 332
UPS5000-E only needs to be equipped with () to easily realize the 2N power supply system, which is simple and convenient to operate?
- A. Synchronous Controller
- B. BSC cable
- C. Parallel card
- D. BSC control panel
Answer: B
NEW QUESTION # 333
One of the highlights of the UPS2000-G series is its high efficiency. It is the first UPS in the industry to pass Energy Star certification.
- A. True
- B. False
Answer: A
NEW QUESTION # 334
What is the maximum capacity of the power module of UPS5000-E?
- A. 40kVA
- B. 20kVA
- C. 50kVA
- D. 30kVA
Answer: C
NEW QUESTION # 335
What is the output power factor of UPS2000-A-(1K-3K)?
- A. 0.9
- B. 0.99
- C. 0.7
- D. 0.8
Answer: D
NEW QUESTION # 336
UPS2000-G monitors the entire parallel system with one card. The parallel system only needs one communication option card to monitor the entire parallel system.
- A. True
- B. False
Answer: A
NEW QUESTION # 337
What kind of inlet and outlet wiring methods can be realized by FusionModule2000 precision power distribution cabinet? (Multiple choice)
- A. Inlet and outlet
- B. Inlet and outlet
- C. Lower inlet and upper outlet
- D. Up-line in and down-line out
Answer: A,B,C,D
NEW QUESTION # 338
UPS5000-E has a wide voltage and frequency input range, which can be used in harsh power grid environments and extend battery life. What is the input voltage range of UPS5000-E at full load?
- A. 305-485V
- B. 105-485V
- C. 138-485V
Answer: C
NEW QUESTION # 339
Lao Wang has been engaged in real estate for many years. Recently, with the trend of new infrastructure, he has entered the data center industry. Lao Wang believes that data centers, like real estate buildings, need to choose economical L1 products.
- A. True
- B. False
Answer: B
NEW QUESTION # 340
UPS500-A-400/500K can support a maximum of () parallel connections and has good scalability.
- A. 0
- B. 1
- C. 2
- D. 3
Answer: D
NEW QUESTION # 341
What is the cabinet depth of Huawei Micro Module 2000? (Multiple choice)
Answer:
Explanation:
B.C.
NEW QUESTION # 342
Which of the following is incorrect about the reliability of NetCol5000-C row-level air conditioners?
- A. It cannot be used in scenarios without raised floors because the condensate drainage cannot be connected to the pipes.
- B. Operators, large corporate headquarters and other large data centers prefer this type of air conditioner.
- C. Dual power supply, two power supplies use automatic switching mode
- D. Small and medium-sized enterprises more often use Netcp15000-A air conditioner with multiple fans for air supply: it can be maintained online.
Answer: A
NEW QUESTION # 343
FusionModule800 temperature control system does not require additional refrigerant if the length of the pipe connecting the internal and external units is within () meters.
- A. 20 meters
- B. 30 meters
- C. 50 meters
- D. 10 meters
Answer: B
NEW QUESTION # 344
......
Huawei H19-402_V1.0 (HCSP-Presales-Data Center Network Planning and Design V1.0) Certification Exam is an excellent certification program for IT professionals who want to enhance their knowledge and skills in data center network planning and design. HCSP-Presales-Data Center Network Planning and Design V1.0 certification is recognized globally and can help IT professionals advance their careers and increase their job opportunities. As such, it is highly recommended for IT professionals who want to stay competitive and up-to-date with the latest trends and technologies in data center network planning and design.
H19-402_V1.0 Premium PDF & Test Engine Files with 543 Questions & Answers: https://actualtests.troytecdumps.com/H19-402_V1.0-troytec-exam-dumps.html